Aurubis warns of lower profit as US plant faces delays
Published
Aurubis has issued a profit warning after furnace defects delayed its new US recycling plant again. Shares in the Hamburg copper group fell sharply after the news on Tuesday. Aurubis, a copper maker based in Hamburg, reported the new problems at its Richmond plant on 24 November 2026.
The plant was meant to lift profit for the Hamburg group over the long term. It can recover up to 200,000 tonnes of copper, nickel, tin, gold, silver and platinum a year. Aurubis invested 740 million euros in the US plant. Investors feel the effect directly, because the share price fell sharply.
According to Aurubis, the furnaces are the heart of the plant and cause lasting problems. Completing the second section, with furnaces three and four, took much longer than planned. On Tuesday, the head office in HafenCity, a district of Hamburg, found serious defects. The company says the suspensions of the melting furnaces need modification. The details were first reported by Hamburger Abendblatt.
In September 2025, the first 40 tonnes of scrap were melted at the plant. Chief executive Toralf Haag had said the plant would make Aurubis a leader in multi-metal recycling in the US. In summer, Aurubis already reported a further delay.
Full capacity during 2026, which the company had expected, will not happen. The group has lowered its profit outlook as a result.
Source: Hamburger Abendblatt
Sources: Hamburger Abendblatt
More Germany news
- Merz Rejects €1.78 Trillion EU Budget Plan at Brussels Summit
- Lidl Recalls Goose Breast Over Salmonella, Best Before 10 December
- GTA 6 causes console crashes on PS5 and Xbox Series X
- DESY and European XFEL improve their X-ray laser world record
- Motorola Signature 27 costs 500 euros more in Germany
- Players find hidden Scarface chainsaw scene in GTA 6
- Jugendzentrum Poing lehnt GTA VI wegen Gewaltdarstellung ab
- Three Werder Bremen athletes are heading to US colleges